Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/21/2019 | ENGINEERING - FINAL | Approved | ||
| 05/14/2019 | ENGINEERING - FINAL | Partial Approval | Engineering has no issues that would prevent a TCO. Complete the work shown on the development plan | |
| 05/08/2019 | ENGINEERING - FINAL | Not ready for Inspection | Work has not been completed. I discussed with the superintendent the requirement for depressed landscaping areas, and requested that he schedule inspections for the sign footings 09028 final landscape. Not ready. They have not started to landscape yet. I reminded the superintendent that they need to remove the dirt when they plant the trees and provide a minimum of 6 inches clear space below curb openings. |
|
| 01/22/2019 | ENGINEERING - FINAL | Not ready for Inspection | Pre-construction meeting with Rick from McManus construction at 269-9783 |