Permit: T18CM04086

Parcel: 11508100C


Addresses:

1110 N STONE AV

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
05/21/2019 ENGINEERING - FINAL Approved
05/14/2019 ENGINEERING - FINAL Partial Approval Engineering has no issues that would prevent a TCO. Complete the work shown on the development plan
05/08/2019 ENGINEERING - FINAL Not ready for Inspection Work has not been completed. I discussed with the superintendent the requirement for depressed landscaping areas, and requested that he schedule inspections for the sign footings
09028 final landscape. Not ready. They have not started to landscape yet. I reminded the superintendent that they need to remove the dirt when they plant the trees and provide a minimum of 6 inches clear space below curb openings.
01/22/2019 ENGINEERING - FINAL Not ready for Inspection Pre-construction meeting with Rick from McManus construction at 269-9783