Inspection Status: Approved
Inspection History: FIRE - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2019 | FIRE - FINAL | Approved | ||
| 07/31/2019 | FIRE - FINAL | Partial Approval | Ok to stock and train/house employees. | |
| 07/25/2019 | FIRE - FINAL | Partial Approval | 1. Ok for TCO to stock and train employees. 2. Address numbers needed on the exterior of building. 3. Locking FDC caps needed. 4. Add FDC sign above FDC. 5. Red Lock needs to be added to FACP breaker. |
|
| 07/24/2019 | FIRE - FINAL | Denied | 1. Need to install al ceiling tiles. 2. 2 EM Lights on 4th Floor need fixed. 3. 4 EM Lights on 1st Floor need fixed including main lobby exit sign. 4. Need to sync horn/strobes in 1st Floor Corridor. 5. Check power to EM Lights in Laundry Room. 6. Horn/Strobes in office and above lobby bar not working. 7. Install remaining exit signs on 1st Floor. |
|
| 06/25/2019 | FIRE - FINAL | Partial Approval | 1. Contractor requesting permission to move in room furniture. 2. Per contractor, sprinkler system is live and monitored. 3. Ok for TCO to stock and supply furniture. |