Permit: T18CM03750

Parcel: 12009309P


Addresses:

4617 S 3RD AV 1

Inspection Status: Approved

Inspection History: ELECTRIC - INTERMEDIATE

Date Description Inspector Results Comments
09/30/2019 ELECTRIC - INTERMEDIATE Approved
09/27/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection Unable to access for inspection. If this inspection does not pass next time, a re-inspection fee will be assessed.
06/17/2019 ELECTRIC - INTERMEDIATE Partial Approval OK to clear electric INCR. still need question answered about the size of the neutral as in previous correction before final.
06/13/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection see previous correction. Specifically the grounding to the new switchgear needs to be addressed before clearance can be turned in. The grounding appears to be too small for the size of the service. Please provide information that it is correct size for that amount of amps. Another failed inspection and no forward progress on this question may result in a reinspection fee.
05/31/2019 ELECTRIC - INTERMEDIATE Partial Approval feeders from switchgear to new 400 amp panel ok. Recommend sending in an RFI as the neutral seems to be too small of gauge. Also where is the grounding for the switchgear?
05/03/2019 ELECTRIC - INTERMEDIATE Partial Approval lunch room, office, tool room, OK to cover
03/20/2019 ELECTRIC - INTERMEDIATE Not ready for Inspection