Inspection Status: Approved
Inspection History: SITE - SEWER
| Date |
Description |
Inspector |
Results |
Comments |
| 04/24/2019 |
SITE - SEWER |
|
Approved |
|
| 04/23/2019 |
SITE - SEWER |
|
Partial Approval |
Not holding pressure test, however connections at existing sewer is good |
| 04/19/2019 |
SITE - SEWER |
|
Partial Approval |
1- Bldg. sewer is okay to cover 60 feet downstream from the previous inspection only. |
| 04/18/2019 |
SITE - SEWER |
|
Not ready for Inspection |
Work incomplete at this time |
| 04/17/2019 |
SITE - SEWER |
|
Partial Approval |
4 inch sewer line approximately 50’ East of site wall. (Approximately 70’ of trenching remaining). Ok to cover progress areas. |
| 04/15/2019 |
SITE - SEWER |
|
Cancelled |
Per phone call with Ron |
| 04/12/2019 |
SITE - SEWER |
|
Not ready for Inspection |
contractor cancelled |
| 04/11/2019 |
SITE - SEWER |
|
Partial Approval |
1- Bldg. sewer from two way clean out east to the block wall only is okay, air pressure test will provided at a later time. |
| 03/12/2019 |
SITE - SEWER |
|
Cancelled |
Cancel by contractor due to rain |