Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 11/30/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Interior walls at 8'-10'; Exterior walls at 8'-10', GL:B/2.5-5, 5/A-B, A/2.5-5. Walls at 8'-12': GL, 2.25/A-B, 1/A-B, A/1-2.5, B/1-2.5. OK to grout progress areas. |
| 11/28/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1- Okay to grout the second lift for the entire bldg. |
| 11/27/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Not ready for Inspection |
Masons were not ready |
| 11/23/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1st lift 0 to 4' |