Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 11/06/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Slab #4, footings and slab. Ok to place concrete. |
| 10/31/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Slab/footings #2 at GL: 2 - 3/A - B. OK to place concrete. |
| 10/23/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Service Building, East portion of building; footings, #4 rebar. Ok to place concrete |
| 10/08/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
10 column pedestals on F1 footings |
| 09/28/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
10 each #F-1 footings to be poured at 16". Ok to place concrete. |