Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2019 | PLUMBING - FINAL | Approved | ||
| 01/16/2019 | PLUMBING - FINAL | Partial Approval | REVIEW OF WATER DISINFECTION REPORT COMPLETED | |
| 01/10/2019 | PLUMBING - FINAL | Not ready for Inspection | Not complete enough | |
| 01/09/2019 | PLUMBING - FINAL | Not ready for Inspection | 1- Contractor cancelled the inspection request | |
| 01/07/2019 | PLUMBING - FINAL | Not ready for Inspection | Customer is requesting a gas meter clearance customer was informed to set up a gas pressure test by plumber and call in inspection 3050 and 3052 at the same time can’t sign off final gas because there’s a lot of gas appliances and related plumbing items that have not been finalized inside the restaurant. I will be advantageous to all concerned that they get the inside ready for their final plumbing so it won’t hold up the meter clearance We have been out here 3 to 4 times for the same inspection and they’re not ready |
|
| 12/24/2018 | PLUMBING - FINAL | Not ready for Inspection | Contractor cancelled | |
| 12/20/2018 | PLUMBING - FINAL | Denied | 1- No one on site at the time of inspection request | |
| 12/17/2018 | PLUMBING - FINAL | Not ready for Inspection | Called contractor ahead. When arrived on site zero personnel on site gates are closed. call contractor again he said the guy should be there I said I would wait another couple minutes I did nobody came I left |