Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 03/13/2019 |
FRAMING |
|
Approved |
|
| 10/26/2018 |
FRAMING |
|
Partial Approval |
Emergency room; ceiling framing and above ceiling MEP's. Ok to set ceiling tiles in progress areas. |
| 09/21/2018 |
FRAMING |
|
Approved |
PHASE II IS COMPLETE |
| 09/21/2018 |
FRAMING |
|
Partial Approval |
PHASE III FRAMING IS APPROVED. |
| 07/12/2018 |
FRAMING |
|
Partial Approval |
BATHROOM HARD LIDS - OK TO SHEETROCK AND TAPE. |