Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/20/2019 | ELECTRIC - FINAL | Approved | AIR BALANCE REPORT COMPLETE ENGINEERING APPROVED |
|
| 04/24/2019 | ELECTRIC - FINAL | Partial Approval | Pending engineering final Except rear storage room Pending air balance report to Bob Sherry in office OK to apply for temporary C of O |
|
| 04/19/2019 | ELECTRIC - FINAL | Partial Approval | except rear storage room | |
| 03/26/2019 | ELECTRIC - FINAL | Partial Approval | SES switchgear ok to energize for test ECO. To remain locked out and tagged out please send clearance a.m. | |
| 02/06/2019 | ELECTRIC - FINAL | Partial Approval | Underground from transformer to switchgear OK to cover. |