Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 08/06/2019 |
BUILDING PRE-SLAB |
|
Approved |
|
| 02/26/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
West generator pad ok to pour |
| 02/20/2019 |
BUILDING PRE-SLAB |
|
Cancelled |
IVRS - RI canceled |
| 01/25/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Stair footing OK to pour. |
| 01/18/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
new slab second-floor OK to pour (finish border rebar) |
| 01/11/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
F1 / C4 footer stairwell East |
| 08/30/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
mezzanine deck ok |
| 08/14/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
Plumb 1st floor Bath, 2 footings for columns at right of switch gear |
| 08/01/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial. Studs-pan deck-rebar. All upper deck and approved but partially completed as initialed on the onsite building plans. Area approved is demarcated and signed. AJ= Superintendent. |
| 04/30/2018 |
BUILDING PRE-SLAB |
|
Partial Approval |
POUR BACKS AT 21 COLUMN LOCATIONS |