Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2020 | REINFORCED MASONRY PRE-GROUT | Approved | competition of CMU Site wall. | |
| 04/14/2020 | REINFORCED MASONRY PRE-GROUT | Partial Approval | first lift for front CMU wall ok for grout. | |
| 10/21/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Top out for all walls except elevator. | |
| 10/21/2019 | REINFORCED MASONRY PRE-GROUT | Approved | Terracon reports for grout from 4' to 8' have been provided. ok to contiune with grout. | |
| 10/17/2019 | REINFORCED MASONRY PRE-GROUT | Denied | Several Lifts have been grouted without inspection, grout crew finishing up as l arrived on site, no inspection made, l instructed contractor to speak to C.O.T. B.O. on this matter. | |
| 10/10/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Elevator shaft finished floor up 4'. Northside columns,3, 4' to 8'4" |