Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/07/2018 | PLUMBING - GAS PRESSURE TEST | Approved | ||
| 03/05/2018 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999 1- SHALL EXTEND THE FURNACE AND WATER HEATER FLU VENT AND TERMINATE 3 FEET ABOVE THE COOLER WHEN THE COOLER IS WITHIN 10 FEET OF THE FLU VENT. 2- SHALL BOND THE GAS LINE WITH A #6 COPPER CONDUCTOR FROM THE WATER HEATER COLD SUPPLY TO THE GAS SUPPLY. 3- SHALL PROVIDE (3) SHEET METAL SCREWS PER JOINT AT THE WATER HEATER DRAFT COLLAR. 4- SHALL PROVIDE A SEDIMENT TRAP FOR THE FURNACE. 5- SHALL PROVIDE THE APPROVED GAS SYSTEM DRAWING ON SITE AT THE TIME OF INSPECTION REQUEST. * |