Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
Permit Number - T18CM01513
Inspection Description - PLUMBING - GAS PRESSURE TEST
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/07/2018 | PLUMBING - GAS PRESSURE TEST | Approved | Detailed list with manufactured housing units that are approved for gas pressure test left with contractor on site | |
09/07/2018 | PLUMBING - GAS PRESSURE TEST | Approved | APPROVED 119, 122, 123, 125, 126, 77, 78, 76, 41, 75, 74, 43, 44, 72.. DENIED 121, 124 |
|
08/23/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | UNITS 47, 51, 52, 53, 54, 55, 57 &58 OK T CLEAR GAS |
|
08/09/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | UNITS OK FOR GAS - 60,62,64,65,66,67,70,71 | |
07/25/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | Homes Approved: 29, 30, 31, 32, 33, 34, 35, 36. 37, 38, 39. Then 79, 81, and 82. GAT= Gas Air Test | |
07/10/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | UNITS 12,18,21-28 ARE OK | |
06/29/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | 13,14,15,16,17,20 ok | |
06/28/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
06/22/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | units 97, 99, 100, 104, 105, 106 ok | |
06/14/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
06/04/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | UNITS 96,101,102 & 107 ONLY | |
05/23/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | LOTS 11,91-95, 84-89 LOT 90 IS ALL ELECTRIC | |
05/16/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | 9 and 10 ok | |
05/10/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | omk units 1, 2, 3, 4, 5, 6, 137 | |
05/03/2018 | PLUMBING - GAS PRESSURE TEST | Partial Approval | HOMES APPROVED ARE 127, 129, 131, 132, 133, 134, 135. APPROVAL IS ONLY FOR NEW WORK FROM METER TO CONNECTION AT MOBILE HOME. MOBILE HOMES ARE NOT INSPECTED. NO GAS CLEARANCE NEEDED ACCORDING TO CONTRACTOR DUE TO MASTER METER. | |
04/20/2018 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | no plans/permits on site |