Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2018 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 05/30/2018 | ELECTRIC - INTERMEDIATE | Partial Approval | Electrician agreed to meet on site to access gutter and to provide requested calculation. | |
| 05/24/2018 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 05/18/2018 | ELECTRIC - INTERMEDIATE | Denied | Remove double lug connecrtion. Correct ground to disconnectr. Correct grounding wire sizing at J Box. Provide D-rate calcs. Non reversable grounding conductor. Rebond to gutter. Tighten connections on dis connects. |