Inspection Status: Approved
Inspection History: ZONING PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 10/16/2022 |
ZONING PROGRESS |
|
Approved |
|
| 07/24/2021 |
ZONING PROGRESS |
|
Partial Approval |
UPDATE: REVIWERS STILL ASSESSING INFORMATION PROVIDED. NEXT STEP: WILL CONDUCT INSPECTION ONCE DETERMINATION HAS BEEN COMMUNICACTED OR WILL CONDUCT PERIODIC INSPECTION IN FIRST WEEK AUGUST. |
| 06/24/2021 |
ZONING PROGRESS |
|
Partial Approval |
ON SITE INSPECTION IN ORDER TO PROVIDE MORE CLARIFICATION ON THE WEST ELEVATION TO PLANNERS. NEXT STEP: WILL COMMUNCIATE WITH PLANNERS REGARDING WEST ELEVATION AND TO DETERMINE IF FURTHER INSPECTIONS ARE REQUIRED, THEN LOOK AT ZONING FINAL. |
| 06/17/2021 |
ZONING PROGRESS |
|
Partial Approval |
INSPECTION AFTER COVID SHUTDOWN: INSPECTION FOUND ALL ELEVATIONS ON SITE MATCHING APPROVED ELEVATIONS IN BOTH T18SA00392 AND T18CM01139. REQUIREMENT IN DDL REQUING MODIFCATION/RESTORATION TO NW CORNER PATIO COVER ABOVE ENTRY HAS BEEN COMPLETED AND MATCH APPROVLS. REPORT GENERATED AND SENT TO ASSOCIATED IID PLANNERS FOR REVIEW AND COMMENT. NEXT STEP: WILL MEET WITH ASSOCIATED PLANNERS AND THEN PLACE ZONING FINAL INTO AP STATUS. |
| 11/27/2019 |
ZONING PROGRESS |
|
Partial Approval |
11/27/19: Conducted first inspection, found project still in demolition stage, will update Planner and set next follow up based on discussion. |