Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
| 06/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Denied | Comply with gable end bracing section C Comply with header schedule Pending approval truss calls Provide stoop at exit door 36 inch landing Per approved site plan south setback reads 4 foot. Garage south set back is 3 foot. Submit as built to site plan or build to plan. Any combustible material within 36” of property line must be fire rated |
|
| 05/31/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | footing OK to pour, however setback issue from previous correction still has not been addressed. Garage to close to the south side property line and overhang is within 3 feet, which per drawings require protection. Recommend seeing a plan reviewer and getting this issue resolved before you pour any concrete. | |
| 01/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | set back on southside does not match drawing have drawing revised. Pour footings per detail around shed with the exception at driveway |