Inspection Status: Approved
Inspection History: BUILDING - FINAL
Permit Number - T18CM00323
Inspection Description - BUILDING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/19/2018 | BUILDING - FINAL | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED | |
09/18/2018 | BUILDING - FINAL | Not ready for Inspection | Air balance report needs to comply and be approved, and other COT department requirements, inspections, and approvals. Met with Tom at K E & G. |
|
08/07/2018 | BUILDING - FINAL | Partial Approval | REVIEW OF WATER CHLORINATION REPORT COMPLETED | |
08/07/2018 | BUILDING - FINAL | Denied | EXHAUST FLOW RATE FOR ERV-1-1 28% LOW | |
08/02/2018 | BUILDING - FINAL | Partial Approval | Submittals today: Air Balance, HVAC Test and Balance Report, Eng released site grading and drainage, Elevator approval. Building Final was given a Partial although complete upon Other COT departments approvals. C of O can be given upon the other approvals as the Building Final is complete. GWest 8-2-2018. | |
07/19/2018 | BUILDING - FINAL | Partial Approval | PA per Building Final done on 7-16-2018, see Final Notes! | |
07/16/2018 | BUILDING - FINAL | Partial Approval | PA. Approved upon completion of all requirements and inspections by other departments. |