Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 11/14/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
AP - 11-14-2018 - AMRTIN1 |
| 08/06/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT TO TOP OF WEST WALL |
| 08/02/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
24' at 4-8' high, closing up west end wall-masonry lift and steel |
| 07/19/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Alignment Rack pad 17-11x7-8 and rebar. Last lift complete to 23'-6". Plus Spec Insp Reports. |
| 07/12/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Lifts 12'8-16'8 and 16'6-20'8, steel reinforcement |
| 07/03/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
8'4 to m12'2 approved. |
| 07/02/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Not ready for Inspection |
|
| 06/28/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
2nd lift |
| 06/14/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1st lift, Horiz/vert corner ties, exp joint rebar, elect conduit stubs, scupper drain pipe. Ready to grout. GWest 6-14-2018 |
| 06/13/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Not ready for Inspection |
|