Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/11/2018 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 01/10/2018 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999 1- SHALL PROVIDE THE REQUIRED TEST GAGE, 15 LBS 1/10TH INCREMENTS FOR THE PRESSURE TEST. 2- SHALL PROVIDE TWO HOLE STRAPS ON THE GAS LINE LOCATED ON TOP OF THE MASONARY WALL. 3- SHALL PROVIDE DOUBLE WALL FLU PIPE ALL THE THRU THE CEILING UP TO THE DRAFT COLLAR. 4 - SHALL PROVIDE A GAS BOND JUMPER. 5- SHALL PROVIDE (3) SHEET METAL SCREWS PER JOINT ON THE WATER HEATER FLU VENT. * |