Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 04/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work completed - close permit |
| 02/09/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
work completed , but needs perm patch - CN |
| 01/03/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
boring and clean up - talked about perm patch areas back next week - CN |
| 12/29/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
boring and will have all trenchs/holes back filled for the long weekend - CN |
| 12/27/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
they had traffic control up and started to pot hole today - cn |
| 12/19/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
precon talked about the details of the job and that they hope to start next week but he will call me with an exact date they are going to start- CN |