Permit: T17RW05458

Parcel: 11810010A

Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
03/15/2018 TDOT-EXCAV GENERAL INSPECTION Approved - work completed - close permit
02/09/2018 TDOT-EXCAV GENERAL INSPECTION Continued they were going to pave today for the walk path. I had them fix a few areas of SG before paving - CN
01/19/2018 TDOT-EXCAV GENERAL INSPECTION Continued no work going on for the contractor they are waiting on a 4ft paver - CN
01/11/2018 TDOT-EXCAV GENERAL INSPECTION Continued digging for the chicaines/water harvesting on the west side of the road. looked at the chicaines that were poured on the east side of the street, also drove the jobsite checking on traffic control and speed humps that were installed - CN
01/04/2018 TDOT-EXCAV GENERAL INSPECTION Continued formed up 3 water harvesting chicains that will be poured tomorrow - CN
12/29/2017 TDOT-EXCAV GENERAL INSPECTION Continued installing speed humps today - CN
12/28/2017 TDOT-EXCAV GENERAL INSPECTION Continued roadway cut for chicains and clearning for the walk path - CN
12/18/2017 TDOT-EXCAV GENERAL INSPECTION Continued stopped by kyle was potholing utilities - CN
12/15/2017 TDOT-EXCAV GENERAL INSPECTION Continued - 8am to 9am precon with meeting with kyle drove the job. asked kyle to get details on walk path/chicanes maybe even set up a meeting with jessie the engineer to make sure that we were all on the same page since there were no real details on the project. Kyle said that they plan to start potholing monday. - CN
12/15/2017 TDOT-EXCAV GENERAL INSPECTION Continued went back out and meet with kyle and jessie the pm for the job. we all talked about the job and what he expected we also talked about adding some bollards so that cars cant drive around speed humps