Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 04/11/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work completed - close permit |
| 01/05/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
sewer bypass still setup - CN |
| 12/11/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- checked traffic control and talked with al with ke&G about the sewer work they are doing on the job. they had just poured a huge lid to a tank on 18th. - CN |
| 11/21/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- work was already started before permit was given - CN |