| 12/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Approved | final walk through at 9:30 to 10:30 with the park guys, they had some small clean up request, but work is completed - close permit | |
| 12/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | started paving alley area - will due a final walk with kyle tomorrow - CN | |
| 12/06/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | kyle called and said they had reworked the alleyway SG. I checked it out it seemed to be good to go. i let kyle know - CN | |
| 12/05/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | stopped by and looked at the area of asphalt they removed and will be working the SG - CN | |
| 11/28/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | walk through of job with kyle and the parks. kyle still has an area of alley way to remove and repave - CN | |
| 11/21/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | walked the job pointed out a few things to fix before final walk through - CN | |
| 11/15/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | weekly meeting , looked at the aphalt that was placed last week while i was in a training - CN | |
| 11/08/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | - prepping to pave the path way today. paved | |
| 11/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | poured header curbs - CN | |
| 11/03/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | looked at the header curbs that will be poured tomorrow at 8:00am - CN | |
| 10/30/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | - kyle had the tester out testing the subgrade by the park - CN | |
| 10/25/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | compaction testing was supposed to be done at 8am and the meeting at 9am was cancelled. i was there around 9am and the testing company still hadnt showed up. kyle and i walked the job and looked at everything they had done since i was out there last. |
|
| 10/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | subgrade density didnt pass - kyle will rework area - CN | |
| 10/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | meeting from 9am to 10am with parks and rec and kyle for the park path job - CN | |
| 10/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | 2nd time out today - conformatech back out to check SG density, First set of test's didnt pass only 91% and 16% moisture - CN | |
| 10/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | - meet with kyle and walked the job and went over work to be done - CN |