Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 11/10/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
SWG permit expired. Still requires asphalt repair on back of sidewalk at the address. SWG notified. |
| 11/06/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
SWG permit; expired; still and open trench behind new sidewalk that needs a permanent asphalt patch. |
| 11/03/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Open trench barricaded off east of the new sidewalk in driveway. Contacted APL that this permit has expired. |
| 11/01/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
3 panels of sidewalk has been replaced match to match but the cross slopes exceed the 2% ADA requirement. However, the cross slope on the two matches are 3.7% on the south side and 2.3% on the north side. Asked Pete and since they are bound by two out-of-spec matches we can accept the sidewalk. Narrow trench behind the sidewalk still needs to be patched. |
| 10/30/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Permanent pavement patch complete on Beverly. Barricades still in place around new concrete sidewalk repair. Still needs a permanent asphalt patch in the business driveway to the east of the sidewalk and out of the ROW. |
| 10/26/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
SWG/APL job, Johnny (APL) forming sidewalk (6") in driveway area. Grade was acceptable. Johnny poured the sidewalk at 11:30a and I stopped by again when the concrete truck was there, no issues. I reminded him that when finishes it to make sure that it does not exceed a 2% cross slope. |
| 10/25/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
SWG/APL project; spoke with concrete foreman Johnny, discussed making the sidewalk in the driveway area 6", placement of expansion for depressed curb and other issues. He will be forming the curb today and pouring tomorrow. |
| 10/25/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Johnny (APL) onsite and finishing the forms for the depressed curb, will pour curb at 11a. Stopped in again around 1p and the curb was poured. He will begin forming the 6" driveway sidewalk and pour that tomorrow. No issues. |