Permit: T17RW04181

Parcel: 130151430


Addresses:

4501 E SYLVANE ST

Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
12/26/2017 TDOT-EXCAV GENERAL INSPECTION Approved NO ISSUES
12/14/2017 TDOT-EXCAV GENERAL INSPECTION Correction Required ALL RAMPS POURED AS ONE PIECE NEEDS EXPANSION JOINT ON BACK
SOME OF THE SIDEWALK ON THE BRIDGE IS OUT OF SPECK
12/14/2017 TDOT-EXCAV GENERAL INSPECTION Correction Required MET WITH MATT S., PETE C., AND GRANITE THEY WILL REPLACE ALL OUT OF SPECK SIDEWALK AND THE NORTHWEST DRIVEWAY RAMP. MATT S. SAID TO FIX THE PANEL ON THE SOUTHWEST RAMP BUT DID NOT NEED TO PLACE EXPANSION JOINT TO KEEP THEM ALL THE SAME
11/28/2017 TDOT-EXCAV GENERAL INSPECTION Continued TRAFFIC CONTROL HAS BEEN REMOVED
10/31/2017 TDOT-EXCAV GENERAL INSPECTION Continued
10/16/2017 TDOT-EXCAV GENERAL INSPECTION Continued SUBGRADE IN SIDEWALK AREA GOOD
10/13/2017 TDOT-EXCAV GENERAL INSPECTION Continued
10/12/2017 TDOT-EXCAV GENERAL INSPECTION Continued
10/11/2017 TDOT-EXCAV GENERAL INSPECTION Continued I LOOKED AT THE SIDEWALK SUBGRADE THATS READY. GOOD TO POUR. PETE WILL MEET ME OUT THERE TOMORROW TO LOOK AT FOOTERS OF PED BRIDGE.