Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 09/29/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
- work completed - close permit |
| 09/25/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
paving the last 2 crossings along 6th and will finish up tomorrow - CN |
| 09/22/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
doing perm patch work should be completed monday - CN |
| 09/20/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- still working on water line, perm patch also going on, talked with them about making sure patch was level and flat |
| 09/05/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- working from 18th to 17th - CN |
| 08/31/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
saw cutting and bump sign put up by bad patch work |
| 08/30/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
still working up to 16th i told them that they needed to fix the temp patching at 16th and that it was sinking. he said he would |
| 08/23/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- no work being done only blue stake was finished- CN |