Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 02/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Job Complete. Final. |
| 01/10/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Stockpile on west side of Fairview south of Glenn needs to be cleaned up and wattled |
| 12/18/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Fairview at Miracle Mile remains closed after Gas leak on Saturday. |
| 09/28/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
1st round of paving scheduled for Wednesday. |
| 09/14/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Milling trench path on Fairview South of Prince Rd. 24hr Lane shift to center lane southbound. Southbound lane closed. |