Inspection Status: Approved
Inspection History: TDOT-Routine Barricade Inspect
| Date |
Description |
Inspector |
Results |
Comments |
| 02/01/2018 |
TDOT-Routine Barricade Inspect |
|
Approved |
Work in alley way completed. |
| 11/15/2017 |
TDOT-Routine Barricade Inspect |
|
Correction Required |
Met with Pete Cannizzaro, lead inspector, and Paul Oberg, Fishel, on-site to point out concrete damage, lack of compaction, and pothole sawcuts in moritorium roadway. |
| 11/13/2017 |
TDOT-Routine Barricade Inspect |
|
Correction Required |
Work is done, no compaction around Century Link equipment or at alleys. Concrete on ramps is broken in multiple locations. Three pieces of asphalt removed in southbound travel lanes, this is a moratorium roadway. |
| 11/02/2017 |
TDOT-Routine Barricade Inspect |
|
Continued |
Fishel has replaced 4 panels of sidewalk and driveway on the east side of Kolb in the project area and made repairs to WCRs of the west side of Kolb. Mini-excavator remains onsite, called and spoke to Paul with Fishel and he said they will have their equipment off the project by the end of the week. |
| 10/26/2017 |
TDOT-Routine Barricade Inspect |
|
Continued |
Fishel has a sub working at the site, ProCorp, who was working on the needed concrete repairs in the project area. Called and spoke with Paul (Fishel); he said he may be at the site later, he is also going to get the permit extended as the cleanup may go into next week. |