Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 01/14/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
PIA work complete per Jack Kokot |
| 08/22/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
gave the permit to matt |
| 08/04/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Permit renewed area looks good. |
| 07/18/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
24 hour setup no conflict. |
| 07/12/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict borderland working on shoulders. |
| 07/05/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict contractor working on the shoulders. |
| 06/27/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict contractor has Westbound and eastbound Starr Pass restricted. |
| 06/09/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict borderland widening Greasewood for turn lane into new Housing Development. |