Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 07/03/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Apron poured back correctly. Final. No Issues. |
| 06/06/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Reminded contractor that permit must be renewed before re-pouring driveway apron. |
| 05/24/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Correction Required |
Met with contractor. Sidewalk is in reject status. Slope over 2% due to slight hump in center. Contractor requested meeting with supervisor. Matt Sierras came to check the DW apron. Agreed that correction needed to be made and he informed the contractor. |
| 05/19/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Correction Required |
Apron rejected. Sidewalk slope exceeds 2% |
| 05/17/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Pouring Apron Today will return 5/19 for final. |
| 05/15/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Discussed how forms need to be adjusted to meet COT and ADA standards. |
| 05/02/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Precon for Sidewalk Install. John Wesley Miller Company |