Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 09/22/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
- work completed - close permit |
| 07/27/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no one on site |
| 07/21/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Correction Required |
Cont, called me ,said he was going to renew permit today |
| 07/10/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict contractor not working but barricade on site. |
| 06/26/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict contractor working on site. |
| 06/21/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict contractor not working but traffic control setup. |
| 06/16/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict all barricade are up contractor not working today. |
| 06/13/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor called for questions on Scupper in sidewalk gave contractor copy of City details for scuppers in sidewalks. |
| 06/08/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
no conflict contractor called wanting forms and subgrade checked for sidewalk and driveway all ok to pour. |
| 05/31/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Correction Required |
talk to contractor he will be renewing the permit today. |
| 05/22/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Correction Required |
correction needed called contractor to fix traffic control and put the caps on form Stakes. |
| 05/03/2017 |
TDOT-EXCAV GENERAL INSPECTION |
|
Not ready for Inspection |
May 1st had precon to do curb cut and today no work on site. |