Permit: T17RW00864

Parcel: 141220280


Addresses:

9255 S RITA RD

Inspection Status: Approved

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
05/24/2017 TDOT-EXCAV GENERAL INSPECTION Approved EVERYTHING IS GOOD AS FAR AS I CAN TELL
05/19/2017 TDOT-EXCAV GENERAL INSPECTION Continued
05/16/2017 TDOT-EXCAV GENERAL INSPECTION Continued NORTHSIDE CURB AND RAMP GOOD
05/09/2017 TDOT-EXCAV GENERAL INSPECTION Continued POURING CURB AND SIDEWALK
05/08/2017 TDOT-EXCAV GENERAL INSPECTION Not ready for Inspection NOT WORKING
05/02/2017 TDOT-EXCAV GENERAL INSPECTION Continued Ramp and sidewalk poured yesterday
Met onsite with TDOT lead Pete C. to approve
Some work remains on new vert curb damaged today.
04/28/2017 TDOT-EXCAV GENERAL INSPECTION Continued Paving from yesterday looks OK
Ramp and sidewalk were not poured this morning per schedule
Rescheduled for Mon.
04/27/2017 TDOT-EXCAV GENERAL INSPECTION Continued Magnum paving N/side of entrance again after grade issues were resolved
04/26/2017 TDOT-EXCAV GENERAL INSPECTION Continued Recheck ramp and sidewalk grade after repairs
Approve to pour
04/25/2017 TDOT-EXCAV GENERAL INSPECTION Continued Ramp area subgrade rejected
Material only wet on top layer Dry and Soft 6 in. below grade
04/24/2017 TDOT-EXCAV GENERAL INSPECTION Continued Check curb forms on N/Side of driveway entrance and approved to pour
04/21/2017 TDOT-EXCAV GENERAL INSPECTION Continued TOOK OUT CURB AND SOME ASPHALT.
FORMED NEW CURB CHECKED SUBGRADE OK.
04/17/2017 TDOT-EXCAV GENERAL INSPECTION Continued Entry way paved against new curb.
Drainage issues possible at new gutterline and being evaluated by contractor
04/12/2017 TDOT-EXCAV GENERAL INSPECTION Continued Working on N/side of entry way on Rita Rd
04/10/2017 TDOT-EXCAV GENERAL INSPECTION Continued Entry curb poured N/Side
04/10/2017 TDOT-EXCAV GENERAL INSPECTION Continued N/Side of entry way curb poured
04/07/2017 TDOT-EXCAV GENERAL INSPECTION Continued 2 visits today for contractor to acheive subgrade density and depth requirements. Approved to pour
03/28/2017 TDOT-EXCAV GENERAL INSPECTION Continued
03/22/2017 TDOT-EXCAV GENERAL INSPECTION Continued
03/15/2017 TDOT-EXCAV GENERAL INSPECTION Continued No ROW work at this time
02/28/2017 TDOT-EXCAV GENERAL INSPECTION Continued No removals at this time