| 12/22/2017 | TDOT-EXCAV GENERAL INSPECTION | Approved | NEILS FUGAL HAS TAKEN OVER AREA WITH PERMIT T17RW05291 | |
| 12/11/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | NOT WORKING IN AREA | |
| 11/28/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | PLATES STILL IN AREA NO ONE WORKING | |
| 11/06/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 11/02/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/31/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/27/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/25/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/16/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/13/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 10/10/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/26/2017 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | Bad asphalt patch crossing concrete driveways at 4015 & 4019 Santa Barbara Ave. | |
| 09/25/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/22/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/21/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/20/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | I'M SEEING SOME REPAIR TO ROW | |
| 09/18/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/14/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 09/11/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/28/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/23/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/22/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/21/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/16/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/15/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/14/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/11/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/10/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/04/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/03/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/02/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 08/01/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/31/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/28/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/27/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/26/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/25/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/24/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/20/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/19/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/18/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/13/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/11/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/10/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/06/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 07/05/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/30/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/29/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | THESE GUYS KEEP A CLEAN JOB SITE | |
| 06/28/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/27/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/26/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | THEY ARE WORKING ON THE OTHER SIDE OF COLUMBUS. CLOSED OUT PERMIT T17RW02205 |
|
| 06/23/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | THEY ARE KEEPING THIS JOB VERY CLEAN | |
| 06/22/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/21/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/20/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/19/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/16/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/15/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/14/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/13/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/09/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/08/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/06/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/05/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/02/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 06/01/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/31/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/30/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/26/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/25/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/24/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/23/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/22/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/19/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/18/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/16/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/15/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/11/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/10/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/09/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/08/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/05/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/04/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/03/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/02/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 05/01/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/28/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/27/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/26/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/25/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/24/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/21/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/20/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/19/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/12/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/06/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/04/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 04/04/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 03/30/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 03/27/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 03/23/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 03/21/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 03/16/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | Working at N/Ecorner Bryant and Santa Barbara | |
| 03/07/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 02/27/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 02/23/2017 | TDOT-EXCAV GENERAL INSPECTION | Correction Required | COMPLANT CALL SPOKE WITH CONTRACTOR ON SITE HE KNOWS HE NEEDS TO MAKE CONCESSIONS TO HOME OWNERS | |
| 02/17/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 02/14/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | ||
| 02/13/2017 | TDOT-EXCAV GENERAL INSPECTION | Continued | PRECON ON PHONE START 2-14-17 |