Inspection History Details
Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/30/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | BUSINESS IS LEFT THE SITE, BUSINESS VACANT ..CLOSE CASE | |
| 04/04/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | MC FIMBRES GRANTS A 6 WEEK EXTENSION BEGINING 4 -13-2018 DUE TO BUSINESS OWNER MOVING OUT OF THE PROPERTY.. | |
| 03/06/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | NOTICE OF VIOLATION ISSUED FOR SITE PLAN REQUIRED DUE TO OUTDOOR ACTIVITY IN I-1 ZONE. | |
| 02/16/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | FAIR AVE IS CLEANED ,, COT CREW ONSITE .. | |
| 02/07/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | GRAVEL PILES HAVE BEEN REMOVED ON FAIR ST. MOST OF THE TRASH WAS REMOVED IN THE RR AREA BUT THERE IS TIRES AND MATTRESSES AND OTHER DEBRIS THERE. | |
| 01/04/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | IMPROVEMENT CONTINUES, LARGE RACKS AND OTHER METAL ITEMS HAVE BEEN REMOVED FROM FRONT AREA, DAMAGED ROLL OFF SCHEDULED TO BE REMOVED ON MONDAY. WILL CONDUCT FOLLOW UP INSPECTION IN 30 DAYS.. PHOTOS TAKEN FOR ADMINISTRATOR. SCANNED IN TO SIRE. | |
| 01/03/2018 | INSP - FOLLOW UP CODE ENFORCE | Approved | ONSITE INSPECTION: MET WITH OWNER, HE ADVISED HE NEEDS ANOTHER 10 DAYS TO CLEAR FRONT AREA. IMPROVEMENT CONTINUES. PARCEL 120-06-366B RIGHT OF WAY WHICH ABUTS FAIR AV HAS LARGE PILES OF GRAVEL / DEBRIS. COLUMBIA ST IS COMPLETELY CLEARED. | |
| 11/24/2017 | INSP - FOLLOW UP CODE ENFORCE | Approved | ONSITE INSPECTION: I DID NOTICE THAT COLUMBIA WHICH IS PRIVATE PROPERTY HAS HAD A HUGE IMPROVEMENT. THE AREA OF 2nd AVE HAS NO VEHICLES PARKED ON THE RIGHT WAY OR SIDEWALK AREA, HOW EVER THERE IS A TWO MAN CREW WORKING ON CUTTING LADLERS IN THE SIDEWALK AREA IN FRONT OF THE ENTRANCES OF THE PROPERTY.. I DID MEET WITH THE OWNER AND HE DID HAVE THE AREA CLEARED. THERE ARE NO BATTERIES ONSITE. HE ADVISED ME THAT HIS MAN POWER WAS DIRECTED TO WORK ON COLUMBIA THESE PASS FEW WEEKS. AS FAR AS THE OVER ALL WORK PLAN HE APPEARS TO BE MOVING FORWARD. HE ALSO STATED THAT AT 420 E AVIATION HE IS CONCENTRATING ON MOVING ALL MATERIALS INSIDE THE FENCE AREA. MAYBE 1 OR 2 ROLL OFF OUTSIDE THE FENCED AREA.. NOTE THIS IS ALSO PRIVATE PROPERTY. HE IS CONFIDENT THIS SHOW BE DONE BY END OF DEC 2017 BUT NO LATER THAN JAN 2018. |
|
| 10/25/2017 | INSP - FOLLOW UP CODE ENFORCE | Approved | ONSITE INSPECTION WITH SUPERVISOR ROMERO: STREETS AND SIDEWALKS CLEAR, THE MOVE CONTINUES, AN UPDATE WAS SENT TO CODE ENFORCEMENT ADMINISTRATOR AND WARD 5 WITH PHOTOS. PER SUPERVISOR ROMERO WILL MONITOR AND RETURN IN 45 DAYS. | |
| 10/24/2017 | INSP - FOLLOW UP CODE ENFORCE | Approved | ONSITE INSPECTION: GREAT IMPROVEMENT STREET AND SIDEWALK IS CLEAR.. THERE IS ONE TRAILER CLOSE TO COLUMBIA WITH MISSING TIRE, FORKLIFT ON THE STREET WITH PALLETS. MANAGER STATES: HE SHOULD THESE AREA CLEAR BY TOMORROW. I DID ADVISED OF OTHER REQUIREMENTS WITH ZONING CODES.. |
|
| 10/20/2017 | INSP - FOLLOW UP CODE ENFORCE | Approved | IMPROVEMENT CONTINUES BUT MINIMAL,, THE COMPANY HAS STAGED MORE MATERIAL IN THE RIGHT OF WAY, BARRLES TIRES AND METAL.. MANAGER STATES HE NOW IS GIVING MATERIAL AWAY TO SPEED THE MOVE.. |