Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/01/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
A new permit has been issued, T18CM06712 on 9-28-18. The work is done and should be calling the inspection soon. At this time the case will be closed. Violation Abated, Close Case. RV. |
| 08/20/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
The person doing the drawings is still working on the drawings and should be taking the plans to submit for approval. Did go over that the approval for the D.D.O. or the Variance has been approved since 7-25-18 and the permit has been withdrawn. The person working on the drawings will be checking on if they need to restart the permit process or have the permit re-opened. Will check in 30 days. RV. |
| 06/27/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
The plans are waiting for the Board of Ajustment to be approved. The date is 7-25-18 for the grace period and final date of the meeting of the approval. Will check in 45 days. RV. |
| 04/12/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Talk to the owner and the draftsman and they did have the neighborhood meeting at the site and no one showed up on 3-31-18 at 12:00 PM. The next step is to set up the variance and should be done by Friday. Will have to wait for the schedule of the Board of Adjustment meeting to check if it gets on the calender for the meeting. Will check in 60 days. RV. |
| 03/26/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
No change to the structures and still on the property. Did call the Architect and left a message to call. RV. |
| 03/26/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Met with Mark Castro and Michael Taku from the historic review and the D.D.O. is now requiring a Board of Adjustment and that has not been requested as of today. Trying to call the owner and the Architect to check on what is going to be done. RV. |
| 03/26/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Received E-mail on the Board of Adjustment has been scheduled on 3-31-18 at 12:00 PM at the site. The letter has gone out to the neighborhood and will check who attends. RV. |
| 02/07/2018 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
The owner is trying to keep the porches where they are at this time and has filed for a D.D.O. The permit for the D.D.O. is T18PRE0010 and has been started on 1-12-18 and waiting for the approval and the grace period time to pass. The permit for the porches and the AC, T17CM08248 and applied on 11-3-17 and has some approvals and pending the approval. Nothing can be done until the D.D.O. has been approved. Will check in 45 days. RV. |
| 11/28/2017 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
The permit for the wall has been issued, T17BU00552 on 11-28-17. The wall has been surveyed and the pins have been placed showing the property line. Still working on the approval for the porches and the AC. RV. |
| 09/28/2017 |
INSP - FOLLOW UP CODE ENFORCE |
|
Approved |
Have been in contact with a Danny Quihuis who has been hired to do the drawings on 9-21-17. The property has been surveyed and the pins have been identified locating the property lines on all sides of the property. Will check in 45 days. RV. |