Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/29/2018 |
ENGINEERING - FINAL |
|
Approved |
|
| 05/25/2018 |
ENGINEERING - FINAL |
|
Partial Approval |
OK FOR TCO |
| 12/22/2017 |
ENGINEERING - FINAL |
|
Continued |
MET WITH JOHN AND LOOKED OVER AN AREA OF CONCERN THAT HE HAD WITH THE ADA INGRESS/EGRESS ACCESS ON THE EAST SIDE OF THE SITE. THEY WILL BE REMOVING THE EXISTING METAL RAILING FROM THE ACCESS POINT TO THE FARTHEST NORTH POINT. IN THIS AREA THEY WILL BE PLACING A LANDING AT THE DOOR AND THEN A RAMP DOWN TO THE EXISTING LEVEL OF THE SIDEWALK. AT THE BOTTOM OF THE RAM THEY WILL NEED TO CONSTRUCT A 60 INCH LANDING FOR THE CHANGE OF DIRECTION THAT IS ADA COMPLIANT. ALSO I HAVE ADVISED JOHN THAT IF THE LADING IS OVER 6 INCHES IN HEIGHT DIFFERENCES IT WOULD BE REQUIRED TO HAVE HANDRAIL ON BOTH SIDES OF THE RAMP. |