Inspection History Details
Inspection Status: Partial Approval
Inspection History: ENGINEERING - FINAL
Permit Number - T17CM08687
Inspection Description - ENGINEERING - FINAL
Inspection Status - Partial Approval
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/07/2019 | ENGINEERING - FINAL | Partial Approval | OK FOR THE TCO AT THIS TIME, ALL REMAINING ITEMS FOR THIS PERMIT WILL BE ADDRESSED WITH THE DEVELOPMENT PACKAGE DP17-0157 PRIOR TO THE FINAL APPROVAL. | |
02/07/2019 | ENGINEERING - FINAL | Approved | I HAVE CONTACTED ARMANDO QUIROZ AND ADVISED HIM THAT THIS FINAL INSPECTION IS BEING APPROVED AT THIS TIME TO ALLOW THE CONTRACTOR TO WORK ON THE FINAL INSPECTION FOR THE STATE.ALL REMAINING ITEMS FOR THIS SITE WILL BE ADDRESSED WITH DP17-0157 PRIOR TO THE ACCEPTANCE OF THAT PERMIT. | |
01/10/2019 | ENGINEERING - FINAL | Partial Approval | SITE WORK IS NOT COMPLETE AT THIS TIME BUT IT IS OK FOR TCO FOR OCCUPANCY | |
12/31/2018 | ENGINEERING - FINAL | Partial Approval | OK FOR A TCO | |
12/31/2018 | ENGINEERING - FINAL | Not ready for Inspection | Pavement and accessible parking has been installed. Ttere is access from the parking lot into the building, but there is no pedestrian access from the street into the building. There is work on the DP to be completed including landscape and sidewalks. |