Permit: T17CM08687

Parcel: 129101290

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T17CM08687

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
12/20/2018 EXCAVATION/LAYOUT REBAR & ZON Approved
05/07/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTERS FOR 6' CMU WALLS PER DETAIL 34 WITH RFI 32" OC
HEAD WALL FOOTERS PER SECTION A-A ONLY FOR STORM DRAINS EAST AND WEST 30" PIPE
04/24/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4 exterior column bases ok to pour
03/21/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GB-3 (2), GB-4 (1), footers F-1 and F-2 ok
03/20/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection cancelled
03/16/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval f7 &f6 footings h2-h3.5 grade beam 1 at column line 3 3-f2 and 1 f6 footings column lin c2-3 ok to pour
03/14/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval elevator pit walls ok
03/07/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footers= F-6 @ C/4 and H/4 , F-3 @ J/7.5 , F-1 @ J/8 and J/10 , entry footers F-4 (5) , F-5(4) , F-9(2) , F-3(4) , F-6(1)
elevator pit
UFER at GB-1 @ C.L. 8 ok
Grade beams= 2 @ 5 , 3 @ H F D , 1 @ 1 and 8
02/26/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval footings d4,e4,f4,f10,g1 10,g18,e6,e7,e9 and d9 ok to pour
02/14/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection