Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T17CM08687
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
05/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTERS FOR 6' CMU WALLS PER DETAIL 34 WITH RFI 32" OC HEAD WALL FOOTERS PER SECTION A-A ONLY FOR STORM DRAINS EAST AND WEST 30" PIPE |
|
04/24/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4 exterior column bases ok to pour | |
03/21/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GB-3 (2), GB-4 (1), footers F-1 and F-2 ok | |
03/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
03/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | f7 &f6 footings h2-h3.5 grade beam 1 at column line 3 3-f2 and 1 f6 footings column lin c2-3 ok to pour | |
03/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | elevator pit walls ok | |
03/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footers= F-6 @ C/4 and H/4 , F-3 @ J/7.5 , F-1 @ J/8 and J/10 , entry footers F-4 (5) , F-5(4) , F-9(2) , F-3(4) , F-6(1) elevator pit UFER at GB-1 @ C.L. 8 ok Grade beams= 2 @ 5 , 3 @ H F D , 1 @ 1 and 8 |
|
02/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | footings d4,e4,f4,f10,g1 10,g18,e6,e7,e9 and d9 ok to pour | |
02/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection |