Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/29/2018 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 06/04/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | Tunnel walls and equipment areas per s2-1 4th lift | |
| 05/24/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 3 Shear Walls 12 Courses Encompassing Electric and Equipment Rms. Wall on North Side of Tube and Retail 12 Courses Rebar per Plan. | |
| 05/17/2018 | REINFORCED MASONRY PRE-GROUT | Approved | Wall for Office and Retail-5 & 6 courses, Wash Tube 7 Courses. Dumpster Fts and 8 Canope Shaft Steel for Lights on North Side |
|
| 04/23/2018 | REINFORCED MASONRY PRE-GROUT | Denied | WALL POURED BEFORE INSPECTIONS | |
| 04/23/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | stem wall ok |