Permit: T17CM08309

Parcel: 130140370


Addresses:

1475 S ALVERNON WY

Inspection Status: Approved

Inspection History: STEM WALL/RETAINING WALL

Date Description Inspector Results Comments
07/10/2018 STEM WALL/RETAINING WALL Approved Garden wall out front, 3'6 high, #5 t&B and #5 verts at 43"OC.
06/20/2018 STEM WALL/RETAINING WALL Partial Approval NORTH WALL OF TUBE LAST COURSE
06/14/2018 STEM WALL/RETAINING WALL Partial Approval SOUTH WALL OF TUBE COMPLETE WITH BOLTS AND BEAM POCKETS, NORTH WALL CUTS MADE AND INSTALLED, NOT APPROVED FOR GROUT AT THIS TIME.
06/13/2018 STEM WALL/RETAINING WALL Partial Approval SOUTH SIDE OF TUNNEL HAS TOP COURSE COMPLETE WITH BOLTS AND BEAM SUPPORT BRACKETS
06/11/2018 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
1- 2ND LIFT NORTH EQUIPMENT ROOM IS OKAY FOR GROUT.
2- TOP OUT ENTRANCE AND EXIT OF TUNNEL ONLY IS OKAY TO CAP, BOND BEAM PROVIDED.
06/04/2018 STEM WALL/RETAINING WALL Not ready for Inspection
05/29/2018 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*
1- STEEL REINFORCEMENT IN CMV WALLS PROVIDED.
2- LADDER WIRE PROVIDED.
3- OKAY TO GROUT THE THIRD LIFT NORTH AND SOUTH TUNNEL WALLS AND THE ENTRANCE AND EXITS OF THE TUNNEL ONLY.
05/25/2018 STEM WALL/RETAINING WALL Not ready for Inspection
05/23/2018 STEM WALL/RETAINING WALL Partial Approval 2nd lift north tullel ok
1st lift east and west tunnel ok
04/23/2018 STEM WALL/RETAINING WALL Denied WALL POURED BEFORE INSPECTIONS