Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T17CM08309

Parcel: 130140370


Addresses:

1475 S ALVERNON WY

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
08/29/2018 EXCAVATION/LAYOUT REBAR & ZON Approved
06/07/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 19 TO 25TH COURSE COMPLETE #5 USED PER LAYOUT
05/22/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Office and Public Areas 1st Lift of 7 Courses, Wall Ajoining Tunnel 1st Lift 6-7 Courses
05/10/2018 EXCAVATION/LAYOUT REBAR & ZON Approved REBAR fo Canopy Bases
05/07/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
05/03/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1. SOUTH OF TUNNEL - OK TO POUR SLAB
2. OFFICE AND BREAKROOM - OK TO POUR SLAB
3. 6 LIGHT COLUMN FOOTINGS OK TO POUR
04/26/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Trench per s4.1 D113
04/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footing and Steel in Tunnel Only
04/12/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ok building footprint
04/11/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection not per plan