Inspection Status: Passed
Inspection History: COT - LCEL - Construction Power
| Date |
Description |
Inspector |
Results |
Comments |
| 05/15/2019 |
COT - LCEL - Construction Power |
GWEST |
Approved |
Entered by CBELL1 - Ufers connected, Gas is bonded, Water is bonded. All sized in accordance with the NEC based on SE Cable size. Main bonding jumper is attached to the can.
TEP was called for Clearance on this new and separate Switch Gear. Spoke with Natalie, ECO. |
| 05/09/2019 |
COT - LCEL - Construction Power |
GWEST |
Correction Required |
Entered by VFLORES1 - Install water bond and gas bond for TEP Clearance |