Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/18/2017 | PLUMBING - GAS PRESSURE TEST | Approved | ||
| 09/12/2017 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 09/08/2017 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | ||
| 08/30/2017 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | Pressure test gas piping system. Gas Correct Vent Connectors; All joints shall be fully made-up and fastened with galvanized or plated sheet metal screws. Tape shall not be used. Fittings shall be listed for the use and may not be modified. Horizontal piping shall slope min ΒΌ inch per foot in an upwardly direction. B-vent shall terminate above the cooler. Relief drain shall be of the same size as the Relief valve, be of approved material and slope downward and terminate to an approved location or drain pan. Carbon monoxide detector required. Gas Bond. |