Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM06198

Parcel: 11712098A


Addresses:

1 S CHURCH AV #2000


Inspection Status: Approved

Inspection History: FIRE - FINAL

Permit Number - T17CM06198

Inspection Description - FIRE - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
12/26/2017 FIRE - FINAL Approved C of O may be given for 20th floor.

Items to be followed up with CBRE.
-Stairwell pressurization
-Atrium smoke control
-Printer for Fire Alarm
-"Fire Command Room" label
-Copy of Annual Fire Alarm Inspection
12/21/2017 FIRE - FINAL Partial Approval General Contractor:

Exit lights need to read "EXIT" only "TIXE" needs to be covered with covering listed with light

Fire extinguisher cabinets need to read " pull here" with arrow pointing in direction and or "open here" with arrow pointing in direction

Escutcheon located West elevator lobby doors needs to be replaced and or cleaned

Electrical panels need to be labeled, breakers numbered and panel names defined

Exit sign on the elevator lobby doors needs to be removed (2)

Elevator light signs need to be covered/ replaced

Open electrical J boxes need to be covered




A temporary certificate of occupancy will be issued for the loading of furniture only and not occupants until December 27th at 4:00 p.m. Fire alarm issues must be resolved and tested prior to the authorization of C of O.




Fire alarm issues:

Smoke detector 20th floor server room is within 3' of the air needs to be relocated to meet code

Provide documentation regarding the audibility/intelligibility test has been performed

Breaker for the power supply 24th floor ELP-24 CKT 1 needs to be red as required by NFPA 70

Electrical panel schedule needs to reflect that Crkt 1 is the FAPS and not telco

Confirm that the fire alarm is sending alarm, trouble and supervisory signals off-site

Confirm the stairwell pressurization is kicking on

Confirm that the atrium smoke control is kicking on

Confirm the elevator recall protocol

Confirm fire alarm activation on 20th floor with water flow







Other building issues (CBRE Responsibility):

Fire alarm has multiple troubles on it that shall be repaired prior to obtaining C of O for 20th floor

Printer for the fire alarm system is not operating

Door to FACP needs a sign that reads "Fire Command Room"

Fire alarm communicators that are obsolete shall be removed from the system

Electrical panel 24th floor needs to be properly labeled and locked out regarding fire alarm, booster panels and applicable amplifiers

Provide current copy of the fire alarm inspection report
12/20/2017 FIRE - FINAL Denied 1. Unable to reach 20th floor without clearance.