Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/16/2020 | PLUMBING - INTERMEDIATE | Approved | ||
| 12/21/2018 | PLUMBING - INTERMEDIATE | Partial Approval | pex piping cannot be against can lights either remove sheet rock or provide pictures showing that was completed from previous correction. Need rough soil work completed and concrete poured in bathroom | |
| 12/14/2018 | PLUMBING - INTERMEDIATE | Not ready for Inspection | pex piping cannot be against can lights. Still need nail plates in many spots in both bathrooms. Need ABS piping to be under test at time of inspection. Need tub under test and concrete poured under tub. Need rough soil work completed and concrete poured in bathroom. Another failed inspection may result in a reinspection fee. | |
| 10/04/2018 | PLUMBING - INTERMEDIATE | Denied | Verify 2:20 amp small appliance circuits kitchen counters provide dedicated refrigerator Outlet secure home runs nail protector throughout seal top plate penetrations stopped inspection too many items to list |