Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T17CM05856

Parcel: 12310001A

Inspection Status: Approved

Inspection History: ELECTRIC - INTERMEDIATE

Date Description Inspector Results Comments
06/07/2019 ELECTRIC - INTERMEDIATE Approved
01/23/2019 ELECTRIC - INTERMEDIATE Partial Approval Installation of new switch gear #S3N-B05 (277-480), S1C-B02 (120-208); new transformer #TR1C-B0T. OK to energize equipment
07/23/2018 ELECTRIC - INTERMEDIATE Partial Approval TRANSFORMER AND MAIN BREAKER #S1N-BO5; BUSS DUCT #S1-BO5. OK TO ENERGIZE EQUIPMENT.
05/08/2018 ELECTRIC - INTERMEDIATE Partial Approval SWITCH GEAR #4 OF 5 AND #5 OF 5. ALL LINES TORQUED AS PER SPECIFICATIONS. OK TO ENERGIZE SYSTEM.
12/19/2017 ELECTRIC - INTERMEDIATE Partial Approval ELECTRIC VAULT PLACE IN SOUTH EAST CORNER OF BUILDING; CONDUIT LINES (4" @2, 5" @3) EAST AND WEST OF VAULT. OK TO PLACE CONCRETE.