Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/10/2018 |
ENGINEERING - FINAL |
|
Approved |
APPROVED PER DROBERTS - 10/04/2018 |
| 08/17/2018 |
ENGINEERING - FINAL |
|
Continued |
INSTALL NEW 4'' POST BARRICADE PER KEY NOTE #22 ON SOUTH SIDE OF BUILDING. AND CUT DOWN REBAR AT TRASH ENCLOSUER WALL. |
| 08/16/2018 |
ENGINEERING - FINAL |
|
Continued |
|
| 08/15/2018 |
ENGINEERING - FINAL |
|
Continued |
|
| 12/14/2017 |
ENGINEERING - FINAL |
|
Partial Approval |
COMPLETE ALL THE SITE WORK AND CLOSE THE DEVELOPMENT PACKAGE PRIOR TO CALLING IN FOR THE FINAL INSPECTION. OK FOR TCO |
| 12/13/2017 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
|