Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2018 | BUILDING - PROGRESS | Approved | ||
| 10/08/2018 | BUILDING - PROGRESS | Partial Approval | Interior mechanical room and interior fire riser room | |
| 10/04/2018 | BUILDING - PROGRESS | Partial Approval | Drywall inspection on elevator mechanical room and exterior fire riser room | |
| 10/03/2018 | BUILDING - PROGRESS | Not ready for Inspection | DECLINED | |
| 10/02/2018 | BUILDING - PROGRESS | Not ready for Inspection | needs additional screws installed | |
| 09/28/2018 | BUILDING - PROGRESS | Partial Approval | DRYWALL ON WEST SIDE OF BUILDING | |
| 09/25/2018 | BUILDING - PROGRESS | Not ready for Inspection | ||
| 09/19/2018 | BUILDING - PROGRESS | Not ready for Inspection | Contractor not ready | |
| 09/17/2018 | BUILDING - PROGRESS | Partial Approval | north side installation. interior first floor only sheet rock on second and third floor. |
|
| 09/14/2018 | BUILDING - PROGRESS | Continued | GATE LOCKED NO ACCESS | |
| 09/12/2018 | BUILDING - PROGRESS | Partial Approval | sheet rock on third floor | |
| 09/10/2018 | BUILDING - PROGRESS | Not ready for Inspection | ||
| 06/29/2018 | BUILDING - PROGRESS | Partial Approval | 3RD FLOOR CONCRETE FLOOR EAST OF ELEVATOR. | |
| 06/25/2018 | BUILDING - PROGRESS | Partial Approval | 3RD FLOOR CONCRETE FLOOR. WEST OF THE ELEVATOR. | |
| 05/22/2018 | BUILDING - PROGRESS | Not ready for Inspection | WORK NOT COMPLETE | |
| 05/22/2018 | BUILDING - PROGRESS | Partial Approval | RETURN INSPECTION 2ND FLOOR DECK OK TO POUR ONLY |