Permit: T17CM05015

Parcel: 11007087B


Addresses:

2660 N ALVERNON WY

Inspection Status: Approved

Inspection History: ELECTRIC - FINAL

Date Description Inspector Results Comments
03/05/2020 ELECTRIC - FINAL Approved ALL DOCUMENTS HAVE BEEN TURNED IN AND APPROVED.
THANK YOU!
02/10/2020 ELECTRIC - FINAL Approved
10/04/2019 ELECTRIC - FINAL Partial Approval Clearance TEP DGC. Final inspection needed when ready.
REOPENED FOR RE-INSPECTION
06/05/2019 ELECTRIC - FINAL Partial Approval ALL LEADS ARE LANDED AND THE SYSTEM HAS BEEN ENERGIZED BY TEP.
06/04/2018 ELECTRIC - FINAL Partial Approval LANDED TO SWITCH GEAR AND GENERATOR
04/17/2018 ELECTRIC - FINAL Partial Approval
02/27/2018 ELECTRIC - FINAL Partial Approval IVRS - Inspection :*
1- VERIFIED THE NEW SES UNIT AND UFER CONDUCTOR HAS BEEN LANDED AT THE SWITCH GEAR.
2- ALL EXTERIOR CONDUITS THROUGH OUT THE SYSTEM IS OKAY.