| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2018 | MECHANICAL - FINAL | Approved | ||
| 03/05/2018 | MECHANICAL - FINAL | Partial Approval | REVIEW OF AIR BALANCE REPORT COMPLETE | |
| 02/26/2018 | MECHANICAL - FINAL | Not ready for Inspection | no work | |
| 02/22/2018 | MECHANICAL - FINAL | Not ready for Inspection | provide access to AHU units revise plans to show changes copper line sets in contact with galv. provide approved filter size pending air balance approval provide secondary drains at AHU provide U.V. protection at line sets provide clearence from VTR to OSA inlets |
|
| 02/21/2018 | MECHANICAL - FINAL | Denied | THE MECHANICAL SYSTEM HAS NOT BEEN ISTALLED PER THE APPROVED PLANS. RESUBMIT THE BALANCE REPORT AFTER THE PLANS HAVE BEEN REVISED. |